A regional ISP needed to expand fiber infrastructure across three rural counties to compete with larger carriers entering their market. Limited internal PM capacity, complex permitting across multiple municipalities, and contractor coordination across simultaneous build zones created significant execution risk.
Back to Case Studies
Telecom
Managed Services
Mid-Size Regional ISP
Regional Fiber Build: 3-County FTTH Expansion
Managed a 3-county fiber-to-the-home buildout for a regional ISP, delivering 14,000+ new passings on time and under budget.
Duration
11 months
Team Size
3 PMs, 2 PMO Analysts
Investment
$1M - $5M
Methodologies
Hybrid
Embedded two senior PMs to lead contractor scheduling, permitting workflows, and weekly stakeholder reporting. Implemented a hybrid tracking framework to manage construction progress alongside make-ready and splicing timelines. Centralized change order management and real-time milestone reporting for the executive team.
Delivered 14,200 new fiber passings across three counties, completed 6 days ahead of schedule, and came in 4% under budget. Client secured a state broadband grant renewal based on project execution data.
Key Results
14,200
Fiber Passings Delivered
6 Days Early
Schedule Performance
4%
Under Budget
3
Counties Covered
Methodologies Applied
Hybrid
Waterfall
Tags
Fiber
FTTH
Telecom
Rural Broadband